EV Charger Installation RAMS Generator (UK)

Generate a site-specific, CDM 2015 compliant Risk Assessment & Method Statement for domestic and commercial EV charger installations in 2 minutes.

✓ CDM 2015 Compliant

Applicable Regulations

Electricity at Work Regulations 1989CDM Regulations 2015Work at Height Regulations 2005

Method Statement — Sequence of Work

  1. Review this RAMS and confirm site conditions match those described before work begins.
  2. Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
  3. Check and don all required PPE, and inspect tools and equipment before use.
  4. Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
  5. Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
  6. On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
  7. Complete the sign-off section at the end of this document before leaving site.

Hazard & Risk Assessment

Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.

Hazard

Electric Shock / Mains Isolation

Control: Isolate main supply at consumer unit, lock out / tag out (LOTO), test dead using proved voltage indicator before terminating.

Initial Risk: HighResidual Risk: Low
Hazard

Ground Trenching / Underground Services

Control: Conduct CAT & Genny scan before excavating cable trench. Hand-dig within 0.5m of known service routes.

Initial Risk: HighResidual Risk: Low
Hazard

Drilling through External Walls

Control: Wear eye protection (BS EN 166) and dust mask (FFP3). Inspect wall for hidden pipework/wiring prior to drilling.

Initial Risk: HighResidual Risk: Low
Hazard

Working Near Vehicles / Traffic on Driveways

Control: Position the work area away from vehicle manoeuvring routes where possible, and use cones or barriers to warn drivers of the work in progress on domestic driveways or car parks.

Initial Risk: HighResidual Risk: Low
Hazard

RCD/RCBO Protection Device Testing

Control: Test and commission the dedicated RCD/RCBO protection device before handover, confirming correct trip times in line with BS 7671 requirements for EV charging circuits.

Initial Risk: HighResidual Risk: Low

Required PPE

BS EN 397 Hard HatBS EN 166 Safety GlassesFFP3 Dust Mask1000V Insulated GlovesBS EN ISO 20345 Safety Boots

Emergency Procedures

Fire

Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.

First Aid / Injury

Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.

Spillage / Environmental Incident

Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.

Emergency Services:999
Site Supervisor / Contact:
Nearest A&E:

Frequently Asked Questions

Do I need a site-specific RAMS for domestic EV charger installs?

Yes. Under CDM 2015, all construction and electrical installation work—including domestic jobs—requires adequate risk planning.

Do I need to keep a copy of this RAMS on site?

Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.