Method Statement — Sequence of Work

  1. Review this RAMS and confirm site conditions match those described before work begins.
  2. Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
  3. Check and don all required PPE, and inspect tools and equipment before use.
  4. Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
  5. Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
  6. On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
  7. Complete the sign-off section at the end of this document before leaving site.

Hazard & Risk Assessment

Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.

Hazard

Manual Handling of Baths, Shower Trays & Sanitaryware

Control: Two-person lift for baths, shower trays and heavy sanitaryware. Use correct lifting technique and avoid twisting while carrying.

Initial Risk: HighResidual Risk: Low
Hazard

Power Tool Use (Drills, Tile Cutters, Jigsaws)

Control: Only use tools with a current PAT test and guards fitted. Use dust extraction on cutting equipment where practical.

Initial Risk: HighResidual Risk: Low
Hazard

Exposure to Silicone, Adhesive & Grout Fumes

Control: Follow the COSHH data sheet for sealants, adhesives and grout. Ensure adequate ventilation in enclosed bathroom spaces.

Initial Risk: HighResidual Risk: Low
Hazard

Working with Existing Plumbing & Water Isolation

Control: Isolate the water supply before disconnecting existing sanitaryware, and confirm no leaks are present before proceeding with removal.

Initial Risk: HighResidual Risk: Low
Hazard

Electrical Safety Near Wet Areas

Control: Install and connect any electrical fittings (extractor fans, shaver sockets) in line with BS 7671's special locations requirements for bathrooms (Section 701).

Initial Risk: HighResidual Risk: Low

Required PPE

BS EN 166 Safety GlassesCut-Resistant GlovesKnee PadsFFP2 Dust MaskSafety Boots

Emergency Procedures

Fire

Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.

First Aid / Injury

Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.

Spillage / Environmental Incident

Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.

Emergency Services:999
Site Supervisor / Contact:
Nearest A&E:

Frequently Asked Questions

Do I need a RAMS for a single domestic bathroom installation?

Yes. Manual handling of sanitaryware and power tool use both carry documented risks, so a site-specific risk assessment is expected even on single domestic jobs.

Do I need to keep a copy of this RAMS on site?

Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.