Wall & Floor Tiling RAMS Generator (UK)

Create a site-specific RAMS for wall and floor tiling work, covering cutting tool safety and adhesive COSHH controls, in under 2 minutes.

✓ CDM 2015 Compliant

Applicable Regulations

COSHH Regulations 2002PUWER 1998Manual Handling Operations 1992

Method Statement — Sequence of Work

  1. Review this RAMS and confirm site conditions match those described before work begins.
  2. Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
  3. Check and don all required PPE, and inspect tools and equipment before use.
  4. Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
  5. Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
  6. On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
  7. Complete the sign-off section at the end of this document before leaving site.

Hazard & Risk Assessment

Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.

Hazard

Tile Cutting Equipment (Wet Saws, Grinders)

Control: Use guarded, PAT-tested cutting equipment with water suppression to limit dust. Ensure operatives are trained on the specific tool.

Initial Risk: HighResidual Risk: Low
Hazard

Exposure to Adhesive & Grout Fumes

Control: Follow the COSHH data sheet for tile adhesives and grouts. Ensure adequate ventilation and use low-solvent products where available.

Initial Risk: HighResidual Risk: Low
Hazard

Manual Handling of Tile Boxes & Stone Slabs

Control: Use trolleys for heavy tile boxes and large-format slabs. Team-lift stone or porcelain slabs over 25kg.

Initial Risk: HighResidual Risk: Low
Hazard

Kneeling & Repetitive Strain During Floor Tiling

Control: Use knee pads and a kneeling mat for floor tiling work, and take regular breaks to reduce repetitive strain from prolonged kneeling.

Initial Risk: HighResidual Risk: Low
Hazard

Silica Dust from Dry-Cutting Tiles

Control: Use water-fed or dust-extracted cutting equipment in preference to dry-cutting, and wear an FFP3 mask where dry-cutting cannot be avoided, in line with HSE guidance on respirable crystalline silica.

Initial Risk: HighResidual Risk: Low

Required PPE

BS EN 166 Safety GlassesCut-Resistant GlovesKnee PadsFFP3 Dust MaskHearing Protection

Emergency Procedures

Fire

Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.

First Aid / Injury

Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.

Spillage / Environmental Incident

Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.

Emergency Services:999
Site Supervisor / Contact:
Nearest A&E:

Frequently Asked Questions

Do I need a RAMS for a small bathroom tiling job?

Yes. Power tool use, manual handling and adhesive/grout exposure all apply even on small domestic jobs, so a documented risk assessment is expected under CDM 2015.

Do I need to keep a copy of this RAMS on site?

Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.