Method Statement — Sequence of Work

  1. Review this RAMS and confirm site conditions match those described before work begins.
  2. Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
  3. Check and don all required PPE, and inspect tools and equipment before use.
  4. Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
  5. Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
  6. On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
  7. Complete the sign-off section at the end of this document before leaving site.

Hazard & Risk Assessment

Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.

Hazard

Radon Gas Exposure During Sub-Floor Works

Control: Ventilate the work area throughout sump installation and testing, minimising time spent in unventilated sub-floor voids and following the radon action plan for the property.

Initial Risk: HighResidual Risk: Low
Hazard

Working in Confined Sub-Floor & Crawl Spaces

Control: Assess access and ventilation before entering sub-floor voids, keeping a second person aware of the work location throughout.

Initial Risk: HighResidual Risk: Low
Hazard

Power Tool Use When Breaking Through Floor Slabs

Control: Use dust extraction on cutting equipment when forming the sump pit, and wear an FFP3 mask throughout.

Initial Risk: HighResidual Risk: Low
Hazard

Fan Unit Electrical Installation

Control: Install and wire the radon sump fan to a fused spur or dedicated circuit in line with BS 7671, positioning it for accessible future maintenance.

Initial Risk: HighResidual Risk: Low
Hazard

Post-Installation Radon Testing

Control: Confirm system effectiveness with a follow-up radon test after installation, in line with UK Health Security Agency guidance.

Initial Risk: HighResidual Risk: Low

Required PPE

FFP3 Dust MaskKnee PadsBS EN 166 Safety GlassesCut-Resistant GlovesCoveralls

Emergency Procedures

Fire

Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.

First Aid / Injury

Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.

Spillage / Environmental Incident

Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.

Emergency Services:999
Site Supervisor / Contact:
Nearest A&E:

Frequently Asked Questions

Does this RAMS cover radon gas exposure risks specific to sub-floor work?

Yes. It includes a control requiring the work area to be ventilated throughout sump installation, minimising time spent in unventilated sub-floor voids.

Do I need to keep a copy of this RAMS on site?

Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.

Get this as a personalised, watermark-free PDF for your job.