Ramsforge

Resin Bound & Block Paving Driveway Installation RAMS Generator (UK)

Generate a site-specific RAMS for resin bound and block paving driveway installation, covering excavation and resin COSHH controls, in 2 minutes.

✓ CDM 2015 Compliant

Applicable Regulations

Manual Handling Operations 1992COSHH Regulations 2002PUWER 1998

Method Statement — Sequence of Work

  1. Review this RAMS and confirm site conditions match those described before work begins.
  2. Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
  3. Check and don all required PPE, and inspect tools and equipment before use.
  4. Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
  5. Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
  6. On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
  7. Complete the sign-off section at the end of this document before leaving site.

Hazard & Risk Assessment

Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.

Hazard

Striking Buried Services During Excavation

Control: Conduct a CAT & Genny scan and consult utility drawings before excavating the driveway base. Hand-dig trial holes near suspected service routes.

Initial Risk: HighResidual Risk: Low
Hazard

Exposure to Resin, Primer & Cement Dust

Control: Follow the COSHH data sheet for resin binder, primer and any cement-based products. Use RPE and ensure adequate ventilation during mixing and laying.

Initial Risk: HighResidual Risk: Low
Hazard

Manual Handling of Aggregates, Kerbs & Slabs

Control: Use a mini-dumper or wheelbarrow for moving aggregate. Team-lift heavy kerbs and paving slabs, keeping loads close to the body.

Initial Risk: HighResidual Risk: Low
Hazard

Plant & Vehicle Movement on Domestic Driveways

Control: Use a banksman for mini-digger or dumper movements on domestic driveways, and keep pedestrians and vehicles clear of the working area.

Initial Risk: HighResidual Risk: Low
Hazard

Weather Sensitivity of Resin Application

Control: Check temperature and rainfall forecasts before mixing and laying resin-bound surfacing, following the manufacturer's application window.

Initial Risk: HighResidual Risk: Low

Required PPE

BS EN 166 Safety GlassesChemical-Resistant GlovesFFP3 Dust MaskBS EN ISO 20345 Safety BootsHi-Vis Clothing

Emergency Procedures

Fire

Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.

First Aid / Injury

Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.

Spillage / Environmental Incident

Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.

Emergency Services:999
Site Supervisor / Contact:
Nearest A&E:

Frequently Asked Questions

Does this RAMS cover the resin binder used in resin bound driveways?

Yes. It includes COSHH-based controls for handling resin binder and primer safely, including ventilation and RPE requirements during mixing and laying.

Do I need to keep a copy of this RAMS on site?

Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.

Get this as a personalised, watermark-free PDF for your job.