Window & Door Glazing Replacement RAMS Generator (UK)

Create a site-specific RAMS for window and door glazing replacement, covering glass handling and working at height, in under 2 minutes.

✓ CDM 2015 Compliant

Applicable Regulations

Manual Handling Operations 1992Work at Height Regulations 2005PUWER 1998

Method Statement — Sequence of Work

  1. Review this RAMS and confirm site conditions match those described before work begins.
  2. Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
  3. Check and don all required PPE, and inspect tools and equipment before use.
  4. Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
  5. Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
  6. On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
  7. Complete the sign-off section at the end of this document before leaving site.

Hazard & Risk Assessment

Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.

Hazard

Cuts from Handling Glass

Control: Use glass-handling gloves and suction lifters. Carry panes vertically and never grip by the edges alone.

Initial Risk: HighResidual Risk: Low
Hazard

Falls from Height (Upper Floor Windows)

Control: Use an appropriate tower or MEWP for upper-floor glazing. Ladders restricted to short-duration ground/first-floor work only.

Initial Risk: HighResidual Risk: Low
Hazard

Manual Handling of Large/Heavy Glass Units

Control: Use a glazing robot or vacuum lifter for large double-glazed units. Team-lift where mechanical aids aren't available.

Initial Risk: HighResidual Risk: Low
Hazard

Disposal of Broken/Damaged Glazing Units

Control: Store broken glass in a dedicated, clearly marked container away from walkways, and dispose of it via a licensed waste carrier.

Initial Risk: HighResidual Risk: Low
Hazard

Working Near Occupied Rooms During Removal

Control: Screen off the work area from occupied rooms during frame and glass removal, and clear the immediate area of furniture and occupants.

Initial Risk: HighResidual Risk: Low

Required PPE

Glass-Handling GlovesBS EN 166 Safety GlassesBS EN ISO 20345 Safety BootsFall Arrest Harness (BS EN 361)Coveralls

Emergency Procedures

Fire

Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.

First Aid / Injury

Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.

Spillage / Environmental Incident

Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.

Emergency Services:999
Site Supervisor / Contact:
Nearest A&E:

Frequently Asked Questions

Does this RAMS cover safe disposal of broken glass?

Yes. It includes safe handling and disposal steps for damaged units, in line with general COSHH and workplace waste handling practice.

Do I need to keep a copy of this RAMS on site?

Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.