Method Statement — Sequence of Work

  1. Review this RAMS and confirm site conditions match those described before work begins.
  2. Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
  3. Check and don all required PPE, and inspect tools and equipment before use.
  4. Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
  5. Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
  6. On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
  7. Complete the sign-off section at the end of this document before leaving site.

Hazard & Risk Assessment

Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.

Hazard

Working at Height for Camera/Sensor Mounting

Control: Use a podium step or tower for mounting positions above 2m. Never overreach from a stepladder when positioning cameras or PIR sensors.

Initial Risk: HighResidual Risk: Low
Hazard

Electric Shock During Cabling & Panel Wiring

Control: Isolate and lock off the relevant circuit before connecting to mains-powered equipment. Use low-voltage cabling wherever possible and test dead before working on any mains connection.

Initial Risk: HighResidual Risk: Low
Hazard

Drilling into External Walls/Structures

Control: Wear eye protection and check for hidden pipework or wiring before drilling cable entry points, particularly on external walls.

Initial Risk: HighResidual Risk: Low
Hazard

Manual Handling of Ladders & Access Equipment

Control: Use correct lifting technique and, where possible, a second person when carrying and positioning ladders or towers around the property.

Initial Risk: HighResidual Risk: Low
Hazard

Data & Power Cable Routing

Control: Route and secure cabling away from foot traffic and pinch points, keeping low-voltage and mains cabling appropriately separated.

Initial Risk: HighResidual Risk: Low

Required PPE

BS EN 166 Safety GlassesBS EN ISO 20345 Safety Boots1000V Insulated GlovesFFP2 Dust MaskHearing Protection

Emergency Procedures

Fire

Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.

First Aid / Injury

Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.

Spillage / Environmental Incident

Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.

Emergency Services:999
Site Supervisor / Contact:
Nearest A&E:

Frequently Asked Questions

Does this RAMS cover working at height to mount CCTV cameras?

Yes. It includes controls for using podium steps or towers when mounting cameras and sensors above 2m, in line with the Work at Height Regulations 2005.

Do I need to keep a copy of this RAMS on site?

Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.