Manual Handling Operations 1992PUWER 1998COSHH Regulations 2002

Method Statement — Sequence of Work

  1. Review this RAMS and confirm site conditions match those described before work begins.
  2. Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
  3. Check and don all required PPE, and inspect tools and equipment before use.
  4. Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
  5. Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
  6. On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
  7. Complete the sign-off section at the end of this document before leaving site.

Hazard & Risk Assessment

Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.

Hazard

Manual Handling of Units & Worktops

Control: Two-person lift for base/wall units and stone or heavy worktops. Use trolleys and worktop lifting suckers to reduce lifting strain.

Initial Risk: HighResidual Risk: Low
Hazard

Power Tool Use (Saws, Drills)

Control: Only use tools with a current PAT test and guards fitted. Use dust extraction on cutting equipment and ensure operatives are trained on each tool.

Initial Risk: HighResidual Risk: Low
Hazard

Exposure to Wood Dust & Adhesive Fumes

Control: Use on-tool dust extraction, work in a ventilated area, and follow the COSHH data sheet for adhesives and sealants used.

Initial Risk: HighResidual Risk: Low
Hazard

Working in an Occupied Domestic Kitchen

Control: Isolate the electricity and water supply to existing appliances before disconnection, and keep the work area segregated from household members during the fit.

Initial Risk: HighResidual Risk: Low
Hazard

Hand-Arm Vibration from Power Tools

Control: Limit continuous trigger time on vibrating tools such as jigsaws and routers, and rotate tasks between operatives to manage daily HAVS exposure.

Initial Risk: HighResidual Risk: Low

Required PPE

BS EN 166 Safety GlassesFFP3 Dust MaskCut-Resistant GlovesHearing ProtectionBS EN ISO 20345 Safety Boots

Emergency Procedures

Fire

Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.

First Aid / Injury

Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.

Spillage / Environmental Incident

Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.

Emergency Services:999
Site Supervisor / Contact:
Nearest A&E:

Frequently Asked Questions

Do I need a RAMS for a single kitchen installation job?

Yes. Any job for a client, including a single domestic kitchen fit, falls under CDM 2015's requirement for adequate risk planning where power tools and manual handling risks are present.

Do I need to keep a copy of this RAMS on site?

Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.

Get this as a personalised, watermark-free PDF for your job.

Generate my RAMS — £15.00