Applicable Regulations
Method Statement — Sequence of Work
- Review this RAMS and confirm site conditions match those described before work begins.
- Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
- Check and don all required PPE, and inspect tools and equipment before use.
- Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
- Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
- On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
- Complete the sign-off section at the end of this document before leaving site.
Hazard & Risk Assessment
Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.
Confined Space Entry (Chambers, Manholes)
Control: Test the atmosphere before entry into any chamber or manhole and use a permit-to-work system with a trained top-man in constant communication.
Striking Buried Services During Excavation
Control: Conduct a CAT & Genny scan and consult utility drawings before excavating, hand-digging trial holes near suspected service routes.
Working in the Public Highway
Control: Set out signage, cones and barriers in line with the New Roads and Street Works Act 1991 (Chapter 8) before starting any work in or near the carriageway or footway.
Waterborne Disease Exposure (Sewage/Contaminated Water)
Control: Wear appropriate waterproof PPE and follow hygiene procedures when working with contaminated water or sewage, covering cuts and washing hands before eating or drinking.
Manual Handling of Valves, Fittings & Equipment
Control: Use mechanical lifting aids for heavy valves, fittings and pumps, team-lifting where mechanical aids aren't practical.
Required PPE
Emergency Procedures
Fire
Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.
First Aid / Injury
Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.
Spillage / Environmental Incident
Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.
Frequently Asked Questions
Does this RAMS cover working in the public highway near live traffic?
Yes. It includes a control requiring signage, cones and barriers to be set out in line with Chapter 8 of the New Roads and Street Works Act 1991 before work begins in or near the carriageway.
Do I need to keep a copy of this RAMS on site?
Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.