Create a site-specific RAMS for cemetery and grounds maintenance work, covering ground stability and machinery hazards, in under 2 minutes.

✓ Site-Specific RAMS

Applicable Regulations

PUWER 1998Manual Handling Operations 1992Health and Safety at Work etc. Act 1974

Method Statement — Sequence of Work

  1. Review this RAMS and confirm site conditions match those described before work begins.
  2. Brief all operatives on the hazards, controls and PPE requirements below (toolbox talk).
  3. Check and don all required PPE, and inspect tools and equipment before use.
  4. Carry out the task in line with the control measures set out in the Hazard & Risk Assessment section below.
  5. Maintain good housekeeping throughout — keep the work area tidy and manage waste and materials safely.
  6. On completion, remove tools and equipment, restore the work area, and report any incidents, near misses or changes in site conditions to the site supervisor.
  7. Complete the sign-off section at the end of this document before leaving site.

Hazard & Risk Assessment

Each hazard is assessed against a standard Likelihood × Severity matrix. “Initial Risk” reflects the risk before any control measures are applied; “Residual Risk” reflects the risk once the stated controls are correctly implemented on site.

Hazard

Unstable or Subsided Ground Around Older Graves

Control: Visually assess ground condition before operating machinery near older grave plots, and avoid heavy plant on areas showing signs of subsidence.

Initial Risk: HighResidual Risk: Low
Hazard

Leaning or Unstable Headstones

Control: Follow the site's headstone safety testing procedure before working near memorials, temporarily supporting or cordoning off any found to be unstable.

Initial Risk: HighResidual Risk: Low
Hazard

Machinery Use (Mowers, Strimmers) Around Memorials & Visitors

Control: Use only guarded, well-maintained equipment, and maintain a respectful working distance from visitors and services in progress.

Initial Risk: HighResidual Risk: Low
Hazard

Working Near Grieving Visitors & Services

Control: Maintain a respectful distance and pause noisy machinery work during funeral services or when visitors are present at nearby graves.

Initial Risk: HighResidual Risk: Low
Hazard

Manual Handling of Grounds Equipment & Memorial Materials

Control: Use correct lifting technique and mechanical aids where possible for heavy mowers, edging equipment and memorial materials.

Initial Risk: HighResidual Risk: Low

Required PPE

BS EN ISO 20345 Safety BootsHearing ProtectionCut-Resistant GlovesBS EN 166 Safety GlassesHi-Vis Clothing

Emergency Procedures

Fire

Stop work immediately, raise the alarm and evacuate to the designated assembly point. Do not attempt to fight a fire beyond your training. Call 999 once safely evacuated if the fire brigade has not already been alerted.

First Aid / Injury

Stop work and alert the nearest first aider or site supervisor. For a serious injury, call 999 immediately and do not move a casualty unless there is immediate danger.

Spillage / Environmental Incident

Stop work, contain the spill using the site's spill kit if safe to do so, and report it to the site supervisor immediately. Do not allow any spillage to enter a drain or watercourse.

Emergency Services:999
Site Supervisor / Contact:
Nearest A&E:

Frequently Asked Questions

Does this RAMS cover the risk of unstable or leaning headstones during grounds maintenance?

Yes. It includes a control requiring the site's headstone safety testing procedure to be followed, with unstable memorials temporarily supported or cordoned off before nearby work continues.

Do I need to keep a copy of this RAMS on site?

Yes. HSE guidance expects a copy of the RAMS — along with the completed sign-off section — to be available on site for the duration of the work, and reviewed if site conditions change.